|
Introduction
|
In
1941, the U.S. Maritime Commission (USMC) embarked on a massive
expansion
of the merchant marine fleet under the auspices of the Emergency
Shipbuilding
Program. |
The
standard Liberty ship, an all-welded cargo ship with a displacement of
7,000 tons, was the centerpiece of this program. The original plan was
to build no more than 60 such ships, contracted under a lend-lease
program
for the British. On March 27, 1941, Congress approved the Defense Aid
Supplemental
Appropriations Act, which envisaged an additional 200 ships for the
lend
lease program. By April, this number had risen to 306 vessels, of which
112 would be Liberty ships. |
After
Pearl Harbor, the US view of the shipbuilding program was fundamentally
revised. Several new programs were initiated, first because of the US
entry
into the war, and second because of German success in the Atlantic in
early
1942, during which time losses were substantially exceeding new
construction.
Eventually, 16 U.S. shipyards delivered a total of 2,580 Liberty ships
ships, by far the largest ever production run of the a single ship
design.
An additional, 119 Liberty ships were produced with modified designs --
colliers, tankers and and aircraft and tank transports -- were also
delivered. |
A
revolutionary aspect of the Liberty shipbuilding program was that a
substantial
portion of ship construction was undertaken off the ways (the berths in
which the keel is laid and from which the ship is eventually launched). |
Most yards had a linear 'conveyor belt' plan. Steel plates and shapes
entered
a holding area in the yard on its inland side, and passed through a
large
prefabrication area where major sections of the ship were constructed.
The sections were then transported on rails or by moveable cranes to
one
the ways, and large whirley cranes lifted them onto the hull for final
assembly. |
Welding
constituted the bulk of this work. A Liberty ship contained almost
600,000
feet of welded joints, and welding labor accounted for about one third
of the direct labor employed in construction. |
Once
the main structures were completed, the vessel was launched and moved
to
the outfitting docks nearby. Another keel was typically laid on the
vacant
way within twenty-four hours. There, final painting, joinery and
electrical
work were completed, and rigging and lifeboats were added. |
The
same day that the final outfitting was completed, the ship was
delivered
to a representative of the USMC, boarded by its crew, and sent to join
one of hundreds of convoys crossing the Atlantic or the Pacific. |